Contact
News Careers Employee Portal Subcontractors
News Careers Employee Portal Subcontractors
I'm searching for
Contact
Higley Construction

About Higley Construction

Higley is one of the most experienced and respected regional construction firms.

About
About
Locations Leadership History Diversity & Inclusion

Projects By Market

Healthcare Education Multi-Family Cultural & Non-Profit Industrial Corporate Hospitality & Entertainment Senior Living Sports & Recreation Government

Projects By Region

Ohio Michigan Pennsylvania New Jersey

Project Delivery

Construction Management Design-Build General Contracting Integrated Project Delivery

Construction Support

Preconstruction Safety Quality Self-Perform Special Projects Construction Yard

Innovation

Building Information Modeling (BIM) & VDC MEP Coordination Lean Construction Sustainability
Scheduling Strategies
Project Controls | June 27, 2024

Higley Builders Blog: Mastering Construction Timelines – Effective Scheduling Strategies

This month, Grace Sauline Rockwell highlights the principles of pull scheduling and lean construction, exploring how these methodologies can transform your project timelines, improve resource management, and ultimately lead to more successful project outcomes. Grace is a leader of the LCI Northern Ohio CoP, a great resource, both nationally and locally, to learn more about Lean Construction.

Read More
Get In Touch
Get In Touch

Welcome to the HIGLEY BUILDERS BLOG, where our experts share their insights and technical expertise on the construction industry.

This month, Grace Sauline Rockwell highlights the principles of pull scheduling and lean construction, exploring how these methodologies can transform your project timelines, improve resource management, and ultimately lead to more successful project outcomes. Grace is a leader of the LCI Northern Ohio CoP, a great resource, both nationally and locally, to learn more about Lean Construction.

MASTERING CONSTRUCTION TIMELINES: EFFECTIVE SCHEDULING STRATEGIES

In the fast-paced and highly competitive world of construction, efficient project management is paramount. One of the most critical aspects of project management is scheduling, which can make or break a project's success. Pull planning and lean construction offer an approach that not only enhances efficiency but also fosters collaboration and reduces waste.

All scheduling efforts aim to develop a reliable plan, to identify and complete critical work on time, and to ensure that owner milestones are met. When potential changes arise, scheduling also plays a critical role in capturing the impact of the change on the project, so that the owner can determine how to proceed, knowing how it will impact their project completion dates.

Pull Planning refers to the method of developing a construction schedule by working backwards from a milestone, “pulling” the required handoffs for each activity into the plan to identify when the work is actually required to not delay progress or interrupt flow. This differs from CPM (critical path method), the traditional scheduling system utilized in construction, which schedules work to occur as soon as possible, once all predecessors are completed.

Lean Construction aims to maximize the value to the customer by eliminating waste in construction. Lean originated from Lean Manufacturing (The Toyota Way), and as the benefit was realized, other industries, such as construction, developed their own tools and methodologies to bring the same benefit to their own projects and systems.

The intention of Pull Planning, in fact the intention of all Lean Construction tools, is to eliminate waste. Some of the wastes that Pull Planning attempts to mitigate are Overproduction, Excess Inventory, and Defects (Rework).

Pull Planning is one of the phases of the Last Planner System. The Last Planner system (LPS) is the Lean scheduling methodology that has the “last planners” (the foremen from our trade partners who plan and assign the work on site) develop and maintain the construction schedule. There are 5 levels of Last Planner System scheduling, which align with PDCA (Plan Do Check Act) methodology:

  • Master Schedule: Establish interim project milestones - the only phase completed by the CM/GC without trade partner involvement.
  • Phase Plan / Pull Plan: Develop a pull plan for the upcoming phase of work with the last planners.
  • Look Ahead Plan: Review the activities that are 6 weeks out to identify and address any constraints before they impact the work onsite.
  • Weekly Work Plan: Foreman schedule the work they have planned for the upcoming week and coordinating amongst the project team to optimize flow.
  • Learning: Discuss which activities occurred per plan and which did not, and identify the reasons for variance of the activities that did not proceed per plan; use these learning to mitigate persistent issues and develop more reliable plans in future weeks.

When Last Planner System has full project team buy-in, it can be a very effective way to optimize flow by creating and executing reliable plans. You minimize situations where you have workers waiting for work, or work waiting for workers.  When some parties are not able or willing to actively participate or make reliable commitments, this can degrade the value of Last Planner System and frustrate those who are participating.

 Last Planner System can bring significant value throughout the Preconstruction and Construction process. Construction Managers typically manage the effort once construction planning begins.  

Many Owners contractually require a CPM (critical path method) schedule to be developed and maintained on their project. When we identify that there is significant value to be added by the collaborative planning and coordination that LPS facilitates, Construction Managers can and should fully utilize LPS on a project with trade partners while simultaneously maintaining a CPM schedule. The most value can be realized when LPS is a contractual requirement from the owner, because then all parties are bought-in to the process, including the owner and design team.

Embracing pull planning and lean construction methodologies can revolutionize the way projects are managed in the AEC industry. By prioritizing efficiency, collaboration, and waste reduction, these approaches not only streamline construction timelines but also enhance overall project quality and stakeholder satisfaction. Implementing pull planning ensures that every step in the process is driven by real-time demand, fostering a more reliable workflow. Meanwhile, the principles of lean construction help in identifying and eliminating waste, leading to cost savings and improved project outcomes.

Grace Sauline Rockwell | Corporate Manager of Project Controls | 11 Years at Higley

Insights
Related

Insights

Stay up to date with the latest news, insights, and related articles from Higley. Explore industry trends, company updates, and thought leadership to stay informed about the world of construction and project management.

Narrow insight results by
Announcements

Celebrating 100 Years of Higley: Building Community, Shaping the Future

In 1925, Albert M. Higley had a simple yet ambitious vision: build a company where relationships mattered as much as results, where doing the right thing wasn’t just a tagline… Read More
Announcements

Decades of Higley: The 1940’s

With the outbreak of World War II and the economy recovered from the last decade, the 1940’s brought about a wave of change for the nation. Higley Construction was able… Read More
Announcements

CEA Highlights the Rock & Roll Hall of Fame

Our Rock & Roll Hall of Fame project is in full swing and the CEA team stopped by to get a closer look at the work our team has been… Read More
News

Decades of Higley: The 1930’s

In a decade defined by both hardship and progress, The Albert M. Higley Company was able to adapt to the changing country. While able to continue working throughout the Great… Read More
Higley
News

Decades of Higley: The 1920's

During the last week of April in 1925, Albert Higley took $2,000 and began his own construction company in Cleveland Ohio. The Albert M. Higley Company was fully incorporated on… Read More
View All Insights
View All Insights
About Locations History Contact
Copyright 2025 Higley Construction Privacy Policy